Officials in Pennsylvania are moving forward on building a replacement for the Fern Hollow Bridge in Pittsburgh, which collapsed on Jan. 28, selecting a team of HDR Inc. and Swank Construction to design and construct the new structure, and the approval of $25.3 million in federal funds for the project.

宾夕法尼亚州运输部发言人亚历克西斯·坎贝尔(Alexis Campbell)通过电子邮件说:“团队“动员到该网站,并开始工作”。

Meanwhile, the National Transportation Safety Board, which has launched an in-depth probe of the collapse, has released an中期报告of the accident, which caused no fatalities but resulted in injuries to 10 people in vehicles that were on the bridge at the time of the collapse.

As expected, the report, issued on Feb. 7, includes factual details, but does not contain findings of the collapse's probable cause. That finding will be part of the NTSB’s final report, which will not be finished for perhaps 12 to 18 months, according to Chair Jennifer Homendy.

The interim report does, however, include some notable specifics. For example, it states, “Initial assessment of bridge components indicates that the collapse initiated at the west end of the structure.”

It adds: “Although certain areas of the welded steel girders were identified as being fracture critical, no primary fractures were found in these areas.”

该报告还指出:“将进行进一步检查,因为拆除了桥梁的碎片并获得了无障碍的访问。”

In addition, the NTSB report describes the 447-ft-long, four-lane bridge in detail, noting that it “was an uncoated weathering steel, three-span, continuous rigid 'K' frame structure with two welded steel girders, welded steel floor beams and rolled steel stringers.”

The report continues. "The ends of the structure rested on reinforced concrete caps on stone masonry abutments. Each girder was additionally supported by two inclined, welded steel frame legs, also made of uncoated weathering steel, which rested atop concrete thrust blocks.”

NTSB also indicated that its investigation will cover the bridge’s design, condition, maintenance, rehabilitation, inspection and load-rating history.

It added that it plans a forensic examination of several of the bridge's structural components, and said, “The recovery of evidence, including extraction and documentation, is expected to be a lengthy process.”

NTSB said, “All aspects of the collapse remain under investigation while the NTSB determines the probable cause, with the intent of issuing safety recommendations to prevent similar events.”

相对简短的报告还叙述了崩溃的细节,许多媒体之前报道了许多人。大约在上午6:40,当桥驶向下方的弗里克公园约100英尺时,四辆乘用车和一个明显的阿勒格尼县巴士港口当局在桥上。根据NTSB的说法,第五辆车从东台上驶出。

The bridge had a posted weight limit of 26 tons.

设计建造团队

On Feb. 4, Pennsylvania Gov. Tom Wolf (D) and Pittsburgh Mayor Ed Gainey (D)announcedthat PennDOT planned to sign an “emergency contract” with the team of Swank and HDR “to immediately begin design efforts and mobilize to remove the existing bridge.”

The Federal Highway Administration said that on Feb. 1, it authorized PennDOT to use $25.3 million in federal formula funding for the project. Of that, $22.6 million will come from the Highway Infrastructure Program’s bridge replacement and rehabilitation funds. The other $2.7 million from the National Highway Performance Program.

FHWA said, “The state decides how to use this funding and FHWA reviews the request.”

PennDOT had explored the use of a different type of funding, from FHWA's Emergency Relief Program, but decided to draw on the formula-funding categories.

Story updated on 2/8/2022 with date that the design-build team began work.