The Shimmick Construction Co. team working on the test pile for the troubled foundation fix of the settling Millennium Tower in San Francisco has switched gears again, this time because of equipment troubles.

Last week, instead of completing the permanent pilot pile by installing the 24-in.-dia steel-encased concrete pile to a depth of about 270 ft, work resumed with the installation of a second outer 36-in.-dia casing for another future 24-in.-dia pile. The outer casing work was approved by the city based on the success of the第一个外壳的安装对于混凝土堆,10月12日至13日。

据Simpson Gumpertz&Heger及其结构性的高级校长Ronald O. Hamburger报道,第二个36英寸Dia套管于10月28日至29日安装,也达到了大约105英尺的深度。1亿美元的基金会修复的录制工程师录制了,就像将保险杠插孔放在扁平轮胎旁边。

加速定居和倾斜

加速定居和倾斜 - 由旨在纠正大约17英寸建筑物定居点的外围堆积升级造成的造成,当时8月20日汉堡停止了工作。

The 645-ft-tall residential condominium, which remains occupied, has sunk a total of about 18 in. since its completion in 2008. The cause is consolidation of Old Bay Clay, according to Hamburger. The fix itself accounts for about 1 in. of the total settlement.

堆积的升级要求沿着建筑物的两侧,在钢制套管内有52个混凝土填充的钢管桩。到8月20日,Shimmick的遗产基金会已安装了33个36英寸二行桩壳和六个24英寸24英寸的钢管桩。

另外五个外壳

据DBI称,汉堡在10月26日向旧金山部提交了一项提案,要求在8月20日停止工作后制定的批准的修订程序,以恢复沿Mission Street的五个,36英寸DIA套管的恢复。

DBI,工程设计评论团队(EDRT)和Dan Brown and Associates(DBA)是一位具有钻探专业知识的岩土技术和基础工程师,批准了与外壳一起前进的建议。

“我们的立场基于36英寸产生的最小整体和解和倾斜。飞行员套管于本月初使用相同的修改程序安装在位置33。” DBI临时董事Patrick O’Riordan在10月27日信致千年塔协会的成员和MTA总经理詹姆斯·扎拉丁(James Zaratin)。

支持条件t

The support was predicated on several conditions, including monitoring building settlement for the first additional casing in real-time, using a survey team and gradient strip mounted on the building façade. “Construction must cease immediately should settlement in the northwest corner exceed ¼-in., and Mr. Hamburger must immediately notify DBI, the EDRT and DBA,” stated the O’Riordan letter.

此外,必须出席DBA工程师“观察,建议和提供指导”,以最大程度地减少和解。此外,DBI高级建筑检查员必须进行日常现场检查,主要与特别检查员进行咨询,以确认工作符合建筑法规。

另一个条件是,如果第二个套管安装导致可忽略的沉降,类似于位于位置33处的飞行员套管,则随后的套管安装将通过每日棱镜测量结构顶部的横向倾斜度进行监控。这封信说:“这些数据将在每天结束时以及每个套管安装结束时传输到DBI,EDRT和DBA。”

在继续前进之前

此外,在每个套管安装的结论结束时,在继续前往下一个外壳之前,改造团队必须暂停所有钻井和套管装置,直到DBI,EDRT,DBA,DBA,Hamburger和Raterofit团队可以查看Prism数据并确保该建筑物仍在在安全范围内。

最后,要求汉堡提供由MAT基金会上的监视器收集的每周调查数据,以跟踪建筑物结算。“应该在西北角建立定居点超过¼-in。每个安装的套管,改造工作将立即停止。”这封信说。

Shimmick has declined to comment on the work, but Hamburger reports replacement parts have been ordered. “We should be running the 24-in. test next week or the week after, depending on how the equipment repair goes,” he says.