Lake Tillery Rehabilitation

Albemarle,N.C.

BEST PROJECTS

CONTRACTOR:PCL建筑

OWNER:North Carolina Dept. of Transportation (NCDOT)

LEAD DESIGN FIRM:艾奕康科技

STRUCTURAL ENGINEER:Modjeski & Masters Inc. (M&M)


Originally constructed in 1927, the open spandrel concrete arch bridge is well known to travelers on both land and water. That made maintaining the bridge’s original architectural features a priority for the two-year, $20.2-million structural rehabilitation, which coincided with a separate, concurrent highway project.

Communication was particularly important for this design-build effort as two engineers-of-record were responsible for different aspects of the rehabilitation. Often PCL Construction consulted both engineers to minimize risk and guarantee successful construction. Using this approach, the PCL team streamlined the process of submitting suggested alternative approaches for consideration.

The collaborative approach also helped integrate hundreds of additional owner-approved repairs, identified during an independent preconstruction inspection, into the overall repair strategy. The team also accommodated an owner-requested alternative surface finish on the concrete barrier wall. Because this finish was not common practice, a two-person grinding and patching crew was detailed to work full time for more than six months to complete finishing in accordance with the owner’s expectations.

Lake Tillerson Bridge

Photo by My Different Perspective

Because repairs to the bridge’s four distinctive arch spans would require partial demolition and extensive underwater work, the project team sequenced construction to minimize hazards to the area’s large number of boaters and jet ski users. Coordination with the North Carolina Wildlife Resources Commission ensured that up-to-date alerts and information bulletins were posted at marinas and other local boat access points.

With demolition activity taking place just 50 ft above the waterline, buoys and work barges enhanced with lights and signage provided an extra measure of safety to boat traffic.

PCL安装的应变计入混凝土拱肋,以监测每个拱门在拆迁期间经历的压力和运动。由于精确切割和仔细重新拆除拆除,拱肋内应力保持在工程师的预定允许公差范围内。