2100 L Street

Washington, D.C.

Award of Merit

KEY PLAYERS

OWNER:Akridge

LEAD DESIGN FIRM:WDG

GENERAL CONTRACTOR:戴维斯建设

SUBCONTRACTORS:Miller & Long DC Inc. (Cast-in-Place Concrete); A. Zahner Co. (Stone Fabrication); Vetro Building Envelope; R. Bratti Associates. Inc. (Custom Metal Fabrication); Schnabel Foundation Co.; R&R Mechanical LLC


Clad in floor-to-ceiling glass curtain wall and veiled with stainless steel architectural metal screening, Washington’s newest trophy office building has close ties with the historic Thaddeus Stevens School next door. But the relationship was almost too close for comfort. Soon after excavation for the tower got underway, unexpected site conditions threatened the school’s structural integrity. Reinforcing the foundation underpinning helped stabilize the school building before any structural damage occurred. While the project team quickly redesigned the excavation plan, task resequencing allowed sitework for 2100 L Street to continue.

Once fully underway, the 259,000-sq-ft project proceeded largely without incident until the closing months. That’s when the COVID-19 outbreak forced the project team to implement social distancing measures and other safety protocols to safely and efficiently achieve substantial completion. Several mock-ups and sample installations were erected on site to ensure that the owner’s quality expectations were being met. Collaboration with the tenant’s design team allowed specialized mechanical, electrical and plumbing systems to be integrated into core-and-shell construction, eliminating the need for subsequent rework.

经过认证的LEED白金,10层,张贴后的现场混凝土建筑,包括园林般的屋顶露台和休息室,可欣赏哥伦比亚特区天际线的壮丽景色。