April 2017
Related Article:
Transportation and Energy Jobs Lead Region’s 2016 Top Starts
单击下面以获取早期版本:
2015
Rank |
Project/Location |
Project Cost ($ Mil.) |
Start/End Dates |
老板 |
Team |
---|---|---|---|---|---|
1 |
Axiall乙烷饼干化学厂
Lake Charles, La. |
3,000 |
June 2016 2019 |
LACC, a Joint Venture of Axiall Corp. and Lotte Chemical Corp.
|
Contractor:CB&I |
2 |
CONTINENTAL’S MISSISSIPPI TIRE PLANT
Clinton, Miss. |
1,400 |
Nov. 2016 2019 |
大陆
|
Contractor/designer not appointed yet—plan for on-boarding in December 2017 |
3 |
SH 288 – TOLL LANES IN HARRIS COUNTY
US 59 to Brazoria County, Texas |
850 |
Oct. 2016 June 2019 |
Texas Dept. of Transportation (TxDOT), Blueridge Transportation Group LLC
|
Contractor:Blueridge Transportation Group LLC |
4 |
LOUIS ARMSTRONG INTERNATIONAL AIRPORT NORTH TERMINAL
New Orleans |
807 |
Jan. 2016 2018 |
Louis Armstrong International Airport
|
Contractor:Hunt-Gibbs-Boh-Metro Designer:Crescent City Aviation Team (a Joint Venture of Leo A Daly, Atkins North America Inc.); Pelli Clarke Pelli; Manning Architects |
5 |
US 181 HARBOR BRIDGE REPLACEMENT
Corpus Christi, Texas |
802 |
2016年8月 2021 |
Texas Dept. of Transportation (TxDOT)
|
Contractor:Flatiron/Dragados LLC |
6 |
US 183 SOUTH
德克萨斯州奥斯汀 |
743 |
April 2016 2020 |
Central Texas Regional Mobility Authority/TxDOT
|
Contractor:Colorado River Constructors, JV of Fluor Enterprises Inc. and Balfour Beatty Infrastructure |
7 |
ALPHA OLEFINS MANUFACTURING PLANT EXPANSION
Geismar, La. |
717 |
2016年2月 Early 2018 |
壳化学公司
|
Contractor:特纳工业有限公司 |
8 |
COMANCHE TRAIL AND TRANS-PECOS NATURAL GAS PIPELINES
瓦哈(Waha)到德克萨斯州的San Elizario/Presidio |
650 |
March 2016 2017 |
Energy Transfer Partners LP
|
|
9 |
石油液体存储终端
洛杉矶山。 |
550 |
June 2016 2017年第三季度 |
Pin Oak Terminals
|
Contractor:Massman Construction Co.; Smith Tank & Steel; EXCEL Group |
10 |
Baytown Steam甲烷改革家(SMR)工厂
Baytown, Texas |
375 |
2016年2月 2018 |
Air Products & Chemicals Inc.
|
Contractor:Technip |
11 |
THE UNION DALLAS
Dallas |
350 |
March 2016 2018年8月 |
红色发展
|
Contractor:DPRConstruction Designer:HKS Inc. |
12 |
JPMORGAN CHASE & CO. LEGACY WEST CAMPUS
Plano, Texas |
300 |
May 2016 Fall 2017 |
JPMorgan Chase&Co./KDC
|
Contractor:贝克集团 Designer:HKS Inc. |
13 |
CHRISTUS SPOHN SHORELINE CAMPUS
Corpus Christi, Texas |
275 |
July 2016 April 2019 |
CHRISTUS Spohn Health System
|
Contractor:麦卡锡建筑公司。 Designer:Perkins+Will |
14 |
THE IRVING MUSIC FACTORY AT LAS COLINAS
Irving, Texas |
200 |
Jan. 2016 Sept. 2017 |
方舟小组
|
Contractor:Skanska Designer:Gensler |
15 |
公园区达拉斯商业混合用途开发
Dallas |
200* |
Jan. 2016 2018 |
MetLife Inc./Trammell Crow Co.
|
Contractor:Balfour Beatty结构 Designer:HKS Inc. |
16 |
SAN PEDRO CREEK IMPROVEMENTS PROJECT
San Antonio |
175 |
Nov. 2016 Summer 2019 |
贝克萨尔县和圣安东尼奥河管理局
|
Contractor:Sundt | Davila, a Joint Venture Designer:Munoz and Co. |
17 |
Donald W. Reynolds Razorback体育场翻新和北端增加
法耶特维尔,方舟。 |
160 |
Dec. 2016 2018年8月 |
University of Arkansas
|
Contractor:CDI-Hunt Designer:Populous, Polk Stanley |
18 |
查尔斯湖传输项目
Lake Charles, La. |
159 |
March 2016 Spring 2018 |
Entergy Louisiana LLC
|
|
19 |
TRINITY RIVER MAIN STEM PUMP STATION AND PIPELINE
Kaufman County, Texas |
140 |
Sept. 2016 Dec. 2018 |
North Texas Municipal Water District
|
Contractor:Garney Construction Designer:Freese and Nichols |
20 |
MERCY HOSPITAL NORTHWEST ARKANSAS – COMMUNITY MASTER PLAN HOSPITAL BED TOWER
Rogers, Ark. |
127 |
May 2016 2020年中 |
怜悯
|
Contractor:麦卡锡建筑公司。 Designer:贝茨建筑师 |
21 |
MARY KAY INC. GLOBAL MANUFACTURING AND R&D FACILITY
Lewisville, Texas |
125 |
Sept. 2016 Q1 2018 |
Mary Kay Inc.
|
Contractor:贝克建筑 Designer:Jacobs Engineering |
21 |
OUR LADY OF THE LAKE CHILDREN'S HOSPITAL
巴吞鲁日,洛杉矶。 |
125* |
Dec. 2016 Summer 2019 |
Our Lady of the Lake Hospital Inc.
|
Contractor:Brasfield & Gorrie Designer:HKS Inc. |
23 |
BAYLOR SCOTT & WHITE SPORTS THERAPY AND RESEARCH AT THE STAR
Frisco, Texas |
120 |
July 2016 2018年2月 |
蓝星陆地唱片
|
Contractor:MEDCO Construction LLC Designer:Perkins+Will |
24 |
AUSTIN PROPER HOTEL & RESIDENCES
德克萨斯州奥斯汀 |
115 |
Sept. 2016 Nov. 2018 |
The Kor Group
|
Contractor:奥斯汀商业 Designer:Handel Architects |
25 |
GRANITE PARK VII
Plano, Texas |
111 |
June 2016 Jan. 2018 |
Granite Properties
|
Contractor:奥斯汀商业 Designer:BOKA Powell |
*Construction Cost |