Rank |
Project/Location |
Project Costs ($ Mil.) |
Start/End Dates |
老板 |
Team |
---|---|---|---|---|---|
1 |
Resorts World Las Vegas
Las Vegas |
4,000 |
May 2015 mid-2018 |
Genting Group
|
DesignSteelman Partners GCW.A. Richardson Builders |
2 |
Lake Mead Intake 3 Low-level Pumping Station
Boulder City, Nev. |
650 |
Oct. 2015 April 2020 |
Southern Nevada Water Authority
|
DesignCH2MHill CMBarnard Construction |
3 |
Roosevelt County Wind Ranch
Between Elida and Dora, N.M. |
430 |
March 2015 Dec. 2015 |
EDF Renewable Energy
|
Design, GCBlattner Energy |
4 |
Lucky Dragon Hotel & Casino
Las Vegas |
373 |
May 2015 Aug. 2016 |
Lucky Dragon LLC Sahara Investments
|
DesignEd Vance & Associates GCThe Penta Building Group |
5 |
100-MW Renewable Energy Generation Facility
Boulder City, Nev. |
275 |
Oct. 2015 Dec. 2016 |
SunPower North America
|
Design, GCSunPower North America |
6 |
Sun Devil Stadium Improvements
Tempe, Ariz. |
256 |
Jan. 2015 July 2017 |
Arizona State University
|
DesignHNTB Corp. and Gould Evans Assoc. GCSundt Construction |
7 |
Switch Supernap Colocation Data Center Building 1
McCarran, Nev. |
211.4 |
Oct. 2015 mid-2016 |
Switch
|
DesignSwitch GCF&P Construction |
8 |
Red Horse 2, 71-MW Wind-Solar Facility
Cochise County, Ariz. |
200 |
Jan. 2015 Aug. 2015 |
D.E. Shaw Renewable Investments
|
Design, GCSwinerton Renewable Energy |
9 |
I-11 Boulder City Bypass (Phase 2)
Boulder City, Nev. |
235 |
April 2015 Oct. 2018 |
Regional Transportation Commission of Southern Nevada
|
DesignThe Berger Group and C.A. Group GCLas Vegas Paving |
10 |
Banner-University Medical Center Phoenix Emergency Dept. and Helipads
Phoenix |
160 |
Oct. 2015 July 2017 |
Banner Health
|
DesignHKS GCDPR建设 |
11 |
Southeast Connector Project (Phase 2)
Washoe County, Nev. |
153 |
June 2015 late 2017 |
Washoe County Regional Transportation Commission
|
DesignCH2MHill and Stantec Consulting CMGranmite Construction |
12 |
Border Security Towers
Cochise County, Ariz. |
125 |
early 2015 N/A |
Dept. of Homeland Security
|
Design, GCEFW |
13 |
Ocotillo Water Reclamation Expansion
Chandler, Ariz. |
122.6 |
Oct. 2015 mid-2017 |
City of Chandler
|
DesignCarollo Engineers GCSundt Construction and McCarthy Building Cos. |
14 |
Ira A Fulton Schools Of Engineering Residence Hall
Tempe, Ariz. |
120 |
Oct. 2015 fall 2017 |
Arizona State University and American Campus Communities
|
DesignSolomon Cordwell Buenz & Associates GCOkland Construction |
15 |
New Entertainment Theater at Monte Carlo
Las Vegas |
100 |
Dec. 2015 late 2016 |
MGM Resorts International
|
DesignSceno-Plus GCMGM Resorts International |
16 |
Valley Health System Henderson Hospital
Henderson, Nev. |
168 |
June 2015 Aug. 2016 |
UHS of Delaware
|
DesignHMC Architects Phoenix GCTurner Construction |
17 |
Sandstone Solar Power Facility
Florence, Ariz. |
80 |
July 2015 early 2016 |
sPower
|
Design, GCSwinerton Renewable Energy |
18 |
Flamingo Water Resource Center, Dual Media Filters Phases 3 and 4
Las Vegas |
80 |
Feb. 2015 April 2017 |
Clark County Water Reclamation District
|
DesignClark County Water Reclamation District CMNevada Water Solutions |
19 |
Caesar's Palace, Julius Tower
Las Vegas |
75 |
fall 2015 mid-2016 |
Caesar’s Entertainment
|
DesignCaesar’s Entertainment GCW.A. Richardson Builders |
20 |
U.S. 491 Roadway Improvement
McKinley County, N.M. |
73.6 |
mid-2015 April 2017 |
NMDOT
|
DesignNMDOT GCFisher Sand and Gravel, Placitas |
21 |
The Motley Apartments, Retail and Parking Garage
Tempe, Ariz. |
65 |
Aug. 2015 early 2017 |
Lennar Multifamily Communities
|
DesignTodd & Associates GCWhiting Turner Contracting |
22 |
Muse Apartments, Parking
Phoenix |
56.9 |
late 2015 spring 2017 |
Lennar Multifamily Communities
|
DesignTodd & Associates GCLennar Multifamily Communities |
23 |
Northwest 215 Bruce Woodbury Beltway
Las Vegas |
52.4 |
Aug. 2015 Aug. 2017 |
Clark County, Las Vegas
|
DesignClark County GCLas Vegas Paving |
24 |
Portland On The Park II Condos, Parking Garage
Phoenix |
50 |
April 2015 late 2016 |
Portland Place Partners
|
DesignDAVIS GCUEBMulti |
25 |
纪念Bowl-U.S。95和i - 215连接器桥
Las Vegas |
47 |
Aug. 2015 late 2017 |
NDOT
|
GCLas Vegas Paving Corp. |
Top Starts Project Details Were Derived From Data Provided by Dodge Data & Analytics, Reports From Within the Public Record and Information Provided by the Project Teams.