Rank |
项目/ Location |
Project Cost ($ Mil.) |
Start Date/ End Date |
Owner/Developer |
Team |
---|---|---|---|---|---|
1 |
ROYAL DUTCH SHELL ETHYLENE CRACKER PLANT
Monaca, Pa. |
6,000 |
Nov. 2017 2020-21 |
Shell Appalachia/Shell Oil Co.
|
GC:Babcock & Wilcox Designer:Shell Appalachia/Shell Oil Co. |
2 |
TRANSCO - ATLANTIC SUNRISE EXPANSION NATURAL GAS PIPELINE
Lebanon, Pa. |
2,961 |
March 2017 2018 |
Williams Partners LP
|
GC:Williams Partners LP |
3 |
MARINER EAST II PIPELINE
Delaware County, Pa. |
2,500 |
June 2017 June 2018 |
Sunoco Logistics Partners L.P. and Energy Transfer Partners
|
GM:Fluor |
4 |
PURPLE LINE LIGHT RAIL - PPP (DESIGN-BUILD)
Various Locations in Maryland |
2,000 |
Aug. 2017 2021 |
Maryland Transit Administration
|
GC:The Lane Construction Corp. Designer:AECOM |
5 |
PENN MEDICINE PAVILION
Philadelphia |
1,500 |
Jan. 2017 Q1 2021 |
Penn Medicine
|
GC:如果博士iscoll + Balfour Beatty Construction Joint Venture Designer:Foster + Partners and HDR |
6 |
HICKORY RUN ENERGY STATION
North Beaver Township, Pa. |
863 |
Aug. 2017 April 2020 |
Siemens Medical Systems Inc.
|
GC:Kiewit Construction Co. Designer:RAR Engineering Group |
7 |
CPV FAIRVIEW ENERGY CENTER
Johnstown, Pa. |
700 |
Oct. 2017 Q1 2020 |
Competitive Power Ventures Inc., Osaka Gas and GE EFS
|
GC:Kiewit Construction Co. Designer:Kiewit Engineering Group Inc. and Stantec |
8 |
EAST CAMPUS BUILDING 2 (DESIGN-BUILD)
Fort Meade, Md. |
616.3 |
Oct. 2017 Aug. 2020 |
US Army Corps of Engineers Baltimore District
|
GC:Clark Construction Group LLC Designer:HOK |
9 |
BACK RIVER WWTP HEADWORKS IMPROVEMENTS
Baltimore |
429.8 |
July 2017 Oct. 2021 |
City of Baltimore Dept. of Public Works
|
GC:Clark/US - Back River LLC (CM at-Risk) Designer:JMT (Johnson Mirmiran Thompson) |
10 |
BIRDSBORO POWER NATURAL GAS-FIRED POWER PLANT
Birdsboro, Pa. |
425 |
May 2017 May 2019 |
Birdsboro Power LLC
|
GC:Kiewit Power District |
11 |
SCUDDER FALLS BRIDGE REPLACEMENT
Bucks County, Pa., and Mercer County, N.J. |
396 |
March 2017 Aug. 2021 |
Delaware River Joint Toll Bridge Commission
|
GC:Trumbull Corp. CM:Hill International Inc. |
12 |
DC UNITED SOCCER STADIUM - AUDI FIELD
Washington, D.C. |
300 |
Feb. 2017 July 2018 |
DC United
|
GC:Turner Construction Co. Designer:Populous Architects PC |
13 |
SECURE NATIONAL HALL
Washington, D.C. |
245 |
Fall 2017 2020 |
Metropolitan Washington Airports Authority
|
GC:Turner Construction Co. |
14 |
INGLESIDE AT KING FARM
Rockville, Md. |
235.3 |
Nov. 2017 Dec. 2019 |
Ingleside Presbyterian Retirement Community Inc., Ingleside Group (WING)
|
GC:The Whiting Turner Contracting Co. Designer:Perkins Eastman |
15 |
SENTINEL SQUARE III
Washington, D.C. |
230 |
Oct. 2017 May 2020 |
Sentinel Square Property LLC
|
GC:Clark Construction Group LLC and Rand Construction Corp. Designer:SmithGroupJJR |
16 |
MLK JR. MEMORIAL LIBRARY (RENOVATION/EXPANSION)
Washington, D.C. |
208 |
May 2017 2020 |
District of Columbia Public Library-MLK Jr. Branch
|
GC:Smoot/Gilbane Joint Venturel Designer:Martinez & Johnson Architects |
17 |
ROYAL DUTCH SHELL ETHYLENE CRACKER PLANT EARLY WORKS PROJECT
Monaca, Pa. |
200 |
2017 Nov. 2017 |
Royal Dutch Shell
|
GC:Trumbull Energy Services/Mascaro JV Owner’s Agent:Jacobs Engineering |
18 |
THE VIEW - PHASE II
Philadelphia |
199 |
Sept. 2017 July 2019 |
Southmoore Owner LLC c/o The Goldenberg Group
|
GC:INTECH Construction Inc. Designer:Niles Bolton Associates |
19 |
CHRISTIANA CARE HEALTH SYSTEM, WOMEN AND CHILDREN'S ADDITION
Newark, Del. |
195 |
April 2017 Nov. 2020 |
Christiana Care Health System
|
CM:Skanska USA Building Inc. Designer:HKS Inc. |
20 |
CHESTER COUNTY HOSPITAL EXPANSION PROJECT
West Chester, Pa. |
185 |
May 2017 May 2021 |
University of Pennsylvania Health System
|
CM:如果博士iscoll Co. Designer:Ballinger |
21 |
CENTER FOR HEALTHCARE TECHNOLOGY
Philadelphia |
170 |
Jan. 2017 May 2019 |
Penn Medicine
|
GC:IMC结构 Designer:Perkins + Will |
21 |
TEMPLE LIBRARY AND CLASSROOM FACILITY
Philadelphia |
170 |
Jan. 2017 Mid-2019 |
Temple University
|
GC:Daniel J Keating Co. Designer:Snohetta Stantec Joint Venture |
23 |
CHEMOURS RESEARCH & DEVELOPMENT BUILDING
Newark, Del. |
165 |
Dec. 2017 March 2020 |
Chemours Co.
|
GC:IMC结构Inc. Designer:L2 Partridge |
24 |
VIRGINIA DEPT. OF GENERAL SERVICES GENERAL ASSEMBLY BUILDING
Richmond |
157 |
Aug. 2017 2020 |
Virginia Dept. of General Services
|
GC:Gilbane Building Co. Designer:Robert A.M. Stern Architects LLP |
25 |
SENECA VALLEY HIGH SCHOOL
Germantown, Md. |
150 |
Sept. 2017 Fall 2020 |
Montgomery County Public Schools Division of Construction
|
GC:Dustin Construction Inc. |